    About the Project

    • A facility with one of the largest battery storage systems in the Czech Republic
    • This energy source can flexibly respond to surpluses or shortages in the grid, and when not in operation, it is in standby mode with zero emissions and no inefficient fuel use
    • It is a modern energy source that includes six gas turbines with a total output of 32.4 MW and a battery storage capacity of 22 MWh
    • Investor: DECCI, a.s., builder E.nest Energy a.s.
    • Contractor and main builder: SIEMENS, s.r.o.
    HUTIRA

    Scope of Technology Supply (collaboration with TECHKO):

    • Production and assembly of the technology for the supply station
    • Gas regulation station RS 24 000/2/1-463 with a capacity of 24,000 m³(N)/hour
    • Installation of a high-pressure industrial gas pipeline with 6 branches for the CX501 gas turbines

    Signing of the contract

    1/2023

    Handing over of complete documentation

    8/2023

    Execution of the Work

    8-11/2023

    Connection of the first gas turbine

    1/2024

    Connection of the remaining turbines

    3/2023

    Final Inspection

    5/2024